Question: 89% Question 4 Consider the following software development project with the following PERT/CPM network diagram D D A 2 B E 1 2 5 You

89% Question 4 Consider the following software development project with the following PERT/CPM network diagram D D A 2 B E 1 2 5 You are required to do the following: (a) Indicate the Earliest Completion Time (ECT) and Latest Completion Time (LCT) for each node in the diagram (9 marks) (b) Give all the possible paths. (4 marks) (e) Indicate the critical path of this project. Justify your answer. (2 marks) (Total: 25 marks) WhatsApp Image Jpeg WhatsApp Image.jpeg