Question: 9 . 1 4 ( a , b , c ) ( 1 . 5 points, 0 . 5 for each subpart ) , 9

9.14(a,b,c)(1.5 points, 0.5 for each subpart),
9.14 Referring to the figure shown below, suppose that Activity O was the last activity in the network and
you were about to start a backward pass.
a. What is the project's duration? (Hint: complete the forward pass)
b. What are the late finish (LF) and late start (LS) values for activities L,M,N, and O?
c. Which activities have slack time? How many days?
 9.14(a,b,c)(1.5 points, 0.5 for each subpart), 9.14 Referring to the figure