Question: 9 . 1 4 ( a , b , c ) ( 1 . 5 points, 0 . 5 for each subpart ) , 9
abc points, for each subpart
Referring to the figure shown below, suppose that Activity was the last activity in the network and
you were about to start a backward pass.
a What is the project's duration? Hint: complete the forward pass
b What are the late finish LF and late start LS values for activities and
c Which activities have slack time? How many days?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
