Question: 9. (14 marks) Draw the network diagram (AON, with CPM) for the following list of activities, Activity Dependency Duration (Days) A 2 B 7 A

9. (14 marks) Draw the network diagram (AON, with

9. (14 marks) Draw the network diagram (AON, with CPM) for the following list of activities, Activity Dependency Duration (Days) A 2 B 7 A 2 D 4 E B.D F 5 3 2. G E.F in the form of blocks of activity nodes as shown below. Early Early Start Duration Finish ACTIVITY Late Late Start Float Finish Fill in the 6 values of each block. Link the block according to the list. Identify the chain of activities which form the critical path and state what is the shortest possible total duration of the project