Question: 9 . 2 0 Dr . Lori Baker, operations manager at Nesa Elec - tronics, prides herself on excellent assembly - line balancing. She has

9.20 Dr. Lori Baker, operations manager at Nesa Elec- tronics, prides herself on excellent assembly-line balancing. She has been told that the firm needs to complete 96 instruments per 24-hour day. The assembly-line activities are:
Task Time (min) Predecessors
A 3-
B 6-
C 7 A
D 5 A, B
E 2 B
F 4 C
G 5 F
H 7 D, E
I 1 H
J 6 E
K 4 G, I, J
50
a) What is the theoretical minimum for the number of worksta- tions that Samuel can achieve in this assembly line?
b) Use the most following tasks heuristic to balance an assembly line for the iStar phone.
c) How many workstations are in your answer to (b)?
d) What is the efficiency of your answer to (b)?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!