Question: 9 ACTIVITY A Cowo NORMAL TIME 5 10 8 6 7 4 4 NORMAL COST $ 7,000 12,000 5,000 4,000 3,000 6,000 7,000 CRASH TIME

9 ACTIVITY A Cowo NORMAL TIME 5 10 8 6 7 4 4
9 ACTIVITY A Cowo NORMAL TIME 5 10 8 6 7 4 4
9 ACTIVITY A Cowo NORMAL TIME 5 10 8 6 7 4 4 NORMAL COST $ 7,000 12,000 5,000 4,000 3,000 6,000 7,000 CRASH TIME 3 7 7 5 6 3 3 CRASH COST $13,000 18,000 7,000 5,000 6,000 7,000 9,000 2.5 points E F G wwo UN b-1. Which activities in order of reduction would be shortened? G-D-A D-G-A 10 A-G-D D-B-C SA b-2. Find the resulting cost to crash. Answer is complete but not entirely correct. Resulting cost to crash $ 5,000 D(6) B(10) A(5) E(7) G(4) C(8) F(4) a-1. Determine the critical path. A-C-E-G A-C-F-GR A-B-D-G A-B-E-G a-2. Determine the early completion time in weeks for the project. Answer is complete and correct. Early completion time 25 weeks

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!