Question: For the data shown, reduce the project completion time by three weeks. Assume a linear cost per week shortened. ACTIVITY A B D E F

For the data shown, reduce the project completion

For the data shown, reduce the project completion time by three weeks. Assume a linear cost per week shortened. ACTIVITY A B D E F G NORMAL TIME 5 10 8 6 7 4 4 NORMAL COST $ 7,000 12,000 5,000 4,000 3,000 6,000 7,000 CRASH TIME 3 7 7 5 6 CRASH COST $13,000 18,000 7,000 5,000 6,000 7,000 9,000 3 b-1. Which activities in order of reduction would be shortened? OD-G-A OA-G-D OD-B-C O G-D-A b-2. Find the resulting cost to crash. Resulting cost to crash