Question: 9. Crashing Exercise C Assume the network and data that follow. Compute the total direct cost for each project duration. If the indirect costs for

9. Crashing Exercise C Assume the network and

9. Crashing Exercise C Assume the network and data that follow. Compute the total direct cost for each project duration. If the indirect costs for each project duration are $400 (19 time units), $350 (18), $300 (17), and $250 (16), compute the total project cost for each duration. Act. Crash Cost (Slope) Maximum Crash Time Normal Time Normal Cost A B D E F G 20 60 40 0 50 100 70 1 2 1 0 3 3 1 3 5 3 10 6 7 5 50 60 70 50 100 90 50 $470 B E Initial project duration 19 5 6 F G 3 3 7 5 D Total direct cost $ 10x