Question: 9...A project has four activities: A, B, C, and D. The budgeted (planned) cost of each activity is $22K, $14K, $12K, and $28K, respectively. The

9...A project has four activities: A, B, C, and D. The budgeted (planned) cost of each activity is $22K, $14K, $12K, and $28K, respectively. The planned percentages complete for the current date are 90%, 80%, 70%, and 20% respectively. The actual percentages complete for the current date are 100%, 90%, 75%, and 10% respectively. The actual cost of the work performed to date is $40K. What is the cost variance for the project?

Over 1.60K

1.21K 1.40K

1.41K 1.60K

Under 1.00K

1.00K 1.20K

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!