Question: A project has four activities: A , B , C , and D . The budgeted ( planned ) cost of each activity is $

A project has four activities: A, B, C, and D. The budgeted (planned) cost of each activity is $22K, $14K, $12K, and $28K, respectively. The planned percentages complete for the current date are 90%,80%,70%, and 20% respectively. The actual percentages complete for the current date are 100%,90%,75%, and 10% respectively. The actual cost of the work performed to date is $40K. What is the BCWS for Activity D?
A) $10.01K - $15K
B) Over $20K
C) $15.01K - $20K
D) $0- $5K
E) $5.01K - $10K

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!