Question: A project has four activities: A, B, C, and D. The budgeted (planned) cost of each activity is $22K, $14K, $12K, and $28K, respectively. The
A project has four activities: A, B, C, and D. The budgeted (planned) cost of each activity is $22K, $14K, $12K, and $28K, respectively. The planned percentages complete for the current date are 90%, 80%, 70%, and 20% respectively. The actual percentages complete for the current date are 100%, 80%, 75%, and 10% respectively. The actual cost of the work performed to date is $40K. What is the cost performance index for the project?
| Activities | Budgeted (Planned) | Planned Percent Complete | Actual Percent Complete |
| A | $22,000 | 19,800 | 22,000 |
| B | 14,000 | 11,200 | 11,200 |
| C | 12,000 | 8,400 | 9,000 |
| D | 28,000 | 5,600 | 2,800 |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts