Given the project information in the following table, what is the probability of completing the National Holiday Toy project in
time units? Hint: Use the NORM.SDISTz TRUE function in Excel to compute the probability. Carry at least decimal
places in all intermediate calculations and the Z value. Enter your final probability answer to decimal places.
Acct. ID Description Predecessor Optimistic a Most Likely m
Pessimistic
b
Activity Time
te
Variance
b a Critical
Design package None x
Design product x
Build package
Secure patent
Build product x
Paint x
Test market x
The probability of completing the project in time units is
Explanation:
For the critical path, the variance is The resulting Zvalue is:
Using the Excel function NORM.SDISTTRUE results in a probability of of finishing the project within time
units.
Worksheet Difficulty: Hard
AStatic Given
the project
information...
Learning Objective: A
Calculate basic Pert
Simulation projections.
Z
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock