Question: A 7 H 2 END START E 8 4 If Activity A is crashed by one week, and all other activities are completed with normal

A 7 H 2 END START E 8 4 If Activity A is crashed

A 7 H 2 END START E 8 4 If Activity A is crashed by one week, and all other activities are completed with normal times, which of the following statements is TRUE? a) The 'early start' times for activity C and activity D will no longer be the same (ESC + ESD) b) Activity G loses one week of slack c) The expected project duration will not change d) Activity D loses one week of slack

Step by Step Solution