Question: Saved If Activity A is crashed by one week, and all other activities are completed with normal times, which of the following statements is TRUE?
Saved If Activity A is crashed by one week, and all other activities are completed with normal times, which of the following statements is TRUE? Question 21 options: The project manager will definitely save money The expected project duration will not change The 'early start' times for activity C and activity D will no longer be the same (ESC ESD) Activity G loses one week of slack Activity D loses one week of slack