Question: ( a ) According to the program evaluation review technique, if a project has an expected time ofQuestion 1 ( a ) A Truck contains

(a) According to the program evaluation review technique, if a project has an expected time ofQuestion 1
(a) A Truck contains both hydraulic brakes with reliability 0.95 and mechanical brakes with
reliability 0.98. Calculate the probability of stopping,
(i) rapidly at high speed, assuming both systems must work
(3 marks)
(ii) at low speed, assuming either system will stop the car
(5 marks)
(b) An engineered system has a hazard rate of 0.01 failure per hour. (1) What is its MTBF
(Mean time between failures)? If the same system has an MTBM (Mean time between
maintenance) of 60 hours, an MDT (Mean down time) of 20 hours, and an MTTR (Mean
time to Repair) of six hours, then, calculate its (2) inherent availability and (3) operational
availability
(7 marks)
(c) For any engineering design of complex systems that you are familiar with, discuss the
importance of drawing/design release management processes involving design changes.
(10 marks)
completion Te of 45 weeks with a standard deviation, of 7 weeks, calculate the probability
of completing it,
(i) within one year (52 weeks)
(2 marks)
(ii) within 38 weeks
(2 marks)
(b) For a company or industry, the strategic management of technology is important. Describe
the technologies that are important for their strategic management of technology.
(9 marks)
(c) Given the project information in the Table Q1 below.
(i) Draw an arrow network diagram
(ii) Show a PDM diagram
(iii) Show all possible paths and identify the critical path
 (a) According to the program evaluation review technique, if a project

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!