Question: Question 3 ( a ) According to the program evaluation review technique, if a project has an expected time of completion Te of 4 5
Question
a According to the program evaluation review technique, if a project has an expected time of completion Te of weeks with a standard deviation, of weeks, calculate the probability of completing it
i
il
within one year weeks
within weeks
marks
marks
b For a company or industry, the strategic management of technology is important. Describe the technologies that are important for their strategic management of technology.
marks