Question: A Activity Optimistic Most Likely Pessimistic Time (ET) B C Time estimates D 31 44 48 22 Start m 40 50 60 31 49 56

Activity Optimistic Most Likely Pessimistic Time (ET) (s) 1. What is the estimated expected (mean) time (in days) for activity C? 2. What is the estimated variance in the time (in days) for activity C? 0 4 9 16 33