Question: Activity Optimistic Most Likely Pessimistic Time (ET) (s) A B C D a 29 44 44 22 9.667 days 14.512 days 0 days 21.778 days

Activity Optimistic Most Likely Pessimistic Time (ET) (s) A B C D a 29 44 44 22 9.667 days 14.512 days 0 days 21.778 days m 31 days 40 49 60 31 Start 53 58 What is the estimated variance in the time for activity C? 72 34 A B D End
 Activity Optimistic Most Likely Pessimistic Time (ET) (s) A B C

Activity Optimistic Most Likely Pessimistic Time (ET) (s) What is the estimated variance in the time for activity C? 9.667 days 14.512 days Odays 21.778 days 31 days