Question: a . At Kobesh Mining Company ( KMC ) , the blasted ore material has a density of 2 . 5 t m 3 and

a. At Kobesh Mining Company (KMC), the blasted ore material has a
density of 2.5tm3 and a swell of 20%. The company wants to
purchase a 5 m 3 power shovel from Komatsu Mining Corporation
with a dipper fill factor of 0.9. The manufacturer's recommended
cycle time for the digging condition is 30 sec for a 90 swing at an
optimum digging depth. The anticipated availability and utilization
are 0.90 and 0.90 respectively. Determine the hourly production rate
of the shovel.