Question: a . Ater installing foundations for the identical towers A and B , a plinth has to be erected for tower B to compensate for
a Ater installing foundations for the identical towers A and a plinth has to be
erected for tower to compensate for the hill slope. On compietion of the plinth a
sighting is taken from its iop to determine fe height of base to be constructed for
tower io ensure final levelling. The foot of each tower is clamped in poation by
a series of securing plates fitted to base A and the plinth.
b The activities to be considered with their estimated duration and manpower
requirements are:
c Produce an "activity on amow" network for the project identirying the critical path
and desemine the minimum duration of the project in days. Show iotal float and
free float on your network.
d Produce a tabulated, job oriented, analyels of the network.
e Produce a bar chart representation of the network and a resource diagram for
the project.
Thauaidi Univemby Open Launing Finginearing
etrrasce unceary
What will be the ellect if the digging of foundation A activity B was edended to
i Days
i days
If the maximum number of men avallable on any day was six, could the project be
completed in the minimum time determined in part assuming the digging of
foundation A took the two days schedaled.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock