Question: a) b) A project whose critical path has an estimated time of 50 days with a variance of 100 has a 25% chance that the

a) a) b) A project whose critical path has an
b)
a) b) A project whose critical path has an
A project whose critical path has an estimated time of 50 days with a variance of 100 has a 25% chance that the project will be completed before day (please round off to two decimal digits) The following represents a project with known activity times. All times are in weeks. Immediate Time Activity Predecessor (weeks) CD F 5 What is the minimum possible time required for completing the project (round it to the nearst whole number)