Question: Using johnson's for 2 machine scheduling, the sequence is Scheduled Order....................Job 1.............................C 2...........................B 3...........................E 4..........................A 5.........................D 6........................F For the schedule developed using Johnson's rule, the
Scheduled Order....................Job
1.............................C
2...........................B
3...........................E
4..........................A
5.........................D
6........................F
For the schedule developed using Johnson's rule, the total length of time taken to complete the six jobs (including the 2nd operation) = hours (enter response as a whole number).
Six jobs are to be processed through a two-step operation. The first operation involves sanding, and the second involves painting Processing times are as follows:
.png)
Operation 1 (hours) Operation 2 (hours) Job 12 11 14 6. 9. 10 1
Step by Step Solution
3.54 Rating (168 Votes )
There are 3 Steps involved in it
Jobs are scheduled as per the time required by the second machine Jobs are arran... View full answer
Get step-by-step solutions from verified subject matter experts
Document Format (1 attachment)
1019-B-C-F-D-F(2182).docx
120 KBs Word File