A bar chart schedule for a project is shown below along with the estimated cost for...
Fantastic news! We've Found the answer you've been seeking!
Question:
Transcribed Image Text:
A bar chart schedule for a project is shown below along with the estimated cost for each activity. The schedule shows the planned timing and duration of the activities at the start of the project. The costs are also estimated at the beginning of the project, and incurred at a constant rate across the duration of the activities. Estimated Time (days) 7 Activity Total Cost 1 2 3 4 5 6 8 9 10 11 12 $700 $1,600 $820 $330 $700 $1,800 $240 $300 $200 $450 $570 $200 $120 Total $8,030 The work begins as scheduled, and after five days of work on the project, a progress report shows the following information about the percent complete and actual costs of each activity: % Complete at end Actual Cost of Activity of 5 days Work to Date A 100% $700 B 75% $1,300 C 50% $400 D 100% $310 E 20% $150 F 0% $0. G 60% $200 H 0% SO I 0% $0 J 60% $375 K 0% $0 L 0% SO M 0% $0 Use the information provided above and Earned Value concepts to answer the following questions: ABCDEFGH 1 K L M a. Draw a cost profile (cumulative cost curve with time on horizontal axis and $ on vertical axis) showing the cumulative project cost over the course of the project for the as- planned condition with estimated costs. b. What is the status of the project in terms of schedule (ahead or behind)? Check SV and SPI. d. c. What is the status of the project in terms of budget (over or under)? Check CV and CPI. What is the estimated total cost of completing all of the work (EAC)? Assume the CPI will remain the same for the remainder of the project. e. What is the expected cost to complete all of the remaining project work (ETC) assuming the work is proceeding as planned? f. Using variance at completion (VAC), determine whether the project is expected to be over or under budget at completion of the project? g. Based on the efficiency that must be maintained in order to complete the current EAC, will it be harder, easier, or the same level of effort to complete the work? Use the "To Complete Performance Index" (TCPI). A bar chart schedule for a project is shown below along with the estimated cost for each activity. The schedule shows the planned timing and duration of the activities at the start of the project. The costs are also estimated at the beginning of the project, and incurred at a constant rate across the duration of the activities. Estimated Time (days) 7 Activity Total Cost 1 2 3 4 5 6 8 9 10 11 12 $700 $1,600 $820 $330 $700 $1,800 $240 $300 $200 $450 $570 $200 $120 Total $8,030 The work begins as scheduled, and after five days of work on the project, a progress report shows the following information about the percent complete and actual costs of each activity: % Complete at end Actual Cost of Activity of 5 days Work to Date A 100% $700 B 75% $1,300 C 50% $400 D 100% $310 E 20% $150 F 0% $0. G 60% $200 H 0% SO I 0% $0 J 60% $375 K 0% $0 L 0% SO M 0% $0 Use the information provided above and Earned Value concepts to answer the following questions: ABCDEFGH 1 K L M a. Draw a cost profile (cumulative cost curve with time on horizontal axis and $ on vertical axis) showing the cumulative project cost over the course of the project for the as- planned condition with estimated costs. b. What is the status of the project in terms of schedule (ahead or behind)? Check SV and SPI. d. c. What is the status of the project in terms of budget (over or under)? Check CV and CPI. What is the estimated total cost of completing all of the work (EAC)? Assume the CPI will remain the same for the remainder of the project. e. What is the expected cost to complete all of the remaining project work (ETC) assuming the work is proceeding as planned? f. Using variance at completion (VAC), determine whether the project is expected to be over or under budget at completion of the project? g. Based on the efficiency that must be maintained in order to complete the current EAC, will it be harder, easier, or the same level of effort to complete the work? Use the "To Complete Performance Index" (TCPI).
Expert Answer:
Answer rating: 100% (QA)
a Cost profile See graph on next page Budgeted at completion BAC for all activities 1745 After 4 wee... View the full answer
Related Book For
Posted Date:
Students also viewed these organizational behavior questions
-
1. Question 1: Make following hierarchy structure of directories. Java is file. Create it in Section 2 And copy in Section 1 and Section 3 2. Use different options of directory and file commands of...
-
Develop a linear regression model: 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 A Year 1992 1993 1994 1995 1996 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007...
-
A 1 defects size B D E 88888888888888888888888888 2 21 3 24 4 16 5 12 6 15 7 5 8 28 9 20 10 31 11 25 12 20 13 24 14 16 15 19 16 10 17 17 18 13 19 22 20 18 21 39 22 30 23 24 24 16 25 19 26 17 27 15...
-
Calculate the weighted average cost of capital for Genedak-Hogan for before and after international diversification. Did the reduction in debt costs reduce the firm's weighted average cost of...
-
Salvador Corporation made an investment in Letter.com, Inc., in exchange for 100,000 options to purchase Letter.coms stock at $20 per share. Since the stock options are not marketable, Salvadors...
-
Develop an M-file function to implement Romberg integration based on Fig. 20.2. Test the function by using it to determine the integral of the polynomial from Example 20.1. Then use it to solve Prob....
-
One calorie is equivalent to (a) \(418.4 \mathrm{~J}\) (b) \(41.84 \mathrm{~J}\) (c) \(4.184 \mathrm{~J}\) (d) \(0.4184 \mathrm{~J}\).
-
A government accounts for inventory on the consumption basis. Why do some accountants believe that it should offset the year-end inventory balance with a fund balancenonspendable when no comparable...
-
1. Explain the objective of the capital asset pricing model 2. Explain the objective of the calculation of the break-even level per units/ revenues 3. When would you use the divisional WACC instead...
-
Assume that you have the following edge-weighted graph. Find the minimum spanning trees using Seattle 11 (1) SF LA Seattle SF 17 LA Las Vegas 20 Las Vegas 14 Denver 15 Alince 5 apalis 10 12 Delles...
-
According to Moyer the appropriate market risk premium to use in the Capital Asset Pricing Model (CAPM) is 8 to 9 percent, relative to 90-day Treasury bill rates, while the appropriate market risk...
-
Three individuals consume a public good, and their demands are expressed as: P1 = 1.5 - 0.005Q (for Q < 300); P = 4.5 0.007Q (for Q < 643); P3 3.0 = 0.002Q (for Q <1500), where P represents price in...
-
3. Explain how a franchise business model works, and discuss its advantages and disadvantages for a company like Domino's who is trying to pursue a new international market. a) How does Franchising...
-
A company is expecting revenues of 2 million in one month's time which it wants to hold for 3 months. The 1 month spot rate is 2.75%. It is concerned that the future 3-month spot rate in one month's...
-
(b) Jake has a current wealth of W. = 2000 and is considering two fair bets X and Y, with an equal chance of winning. Jake can bet any amount of money for either X or Y to win. His utility functions...
-
(c) Mary has an initial wealth of $1. She can invest an amount x from it in non-dividend- paying stocks, y in bonds and the rest in cash. Consider three different scenarios as follows where cash...
-
It is now January 1 . You plan to make a total of 5 deposits of $ 6 0 0 each, one every 6 months, with the first payment being made today. The bank pays a nominal interest rate of 1 0 % but uses...
-
What services are provided by the provincial and territorial governments?
-
Cavanaugh Construction specializes in designing and building custom homes. Business has been excellent, and Cavanaugh projects a 10% growth rate for the foreseeable future. The company just paid a...
-
Reconsider the Connecticut Computer Company of the previous problem assuming the firm has experienced some difficulties and its EBIT has fallen to $8,000. a. Reconstruct the three-column chart...
-
Should the project being considered in the previous problem be accepted or rejected based on IRR? (Hint: Start by guessing 11% for IRR.)
-
Describe the process of valuing the entrepreneurs ownership interest in a two-stage investment. Refer to Tables 13.10 and 13.13. Data from table 13.10 Data from table 13.13 Market potential...
-
Euro Exchange Rates. The exchange rate that we consider is the amount of euros that one can purchase for one U.S. dollar. We have \(T=699\) daily observations from the period April 1, 2005, through...
-
Evaluate the current yield curve level and structure using the following screens: a. YCRV or GC to access yield curves. b. FWCV to determine implied forward rates. c. USoo03M, USoo06M, USoo09M, and...
Study smarter with the SolutionInn App