Question: A bar graph with time on the horizontal axis and activities to be scheduled on the vertical axis is a _ _ _ _ _

A bar graph with time on the horizontal axis and activities to be scheduled on the vertical axis is a ________.
Select one:
A.
flow chart
B.
pie chart
C.
PERT chart
D.
Gantt chart
E.
scatter plot