Question: A best practice for Data Capture and Verification on a project is to collect remaining duration (RD) for schedule progress and percent complete for cost
A best practice for Data Capture and Verification on a project is to collect remaining duration (RD) for schedule progress and percent complete for cost completion. Select the option for breaking the tie between percent complete and RD. Collect actual start and actual finish data consistently