Question: A biometrics firm has a facial recognition program with multiple components and project managers. The project manager from the mobile device division escalates a vendor
A biometrics firm has a facial recognition program with multiple components and project managers. The project manager from the mobile device division escalates a vendorrelated risk to the program manager. After assessing the risk, the program manager determines that this risk may impact other projects within the program. However, this risk has a low degree of impact and probability of occurring. What should the program manager do first?
A Brainstorm with the project managers to develop an appropriate risk response.
B Add the risk details and analysis to the program risk register.
C Obtain a risk reserve from the executive sponsor, and execute a contingency plan.
D Ignore this risk
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock