Question: A biometrics firm has a facial recognition program with multiple components and project managers. The project manager from the mobile device division escalates a vendor

A biometrics firm has a facial recognition program with multiple components and project managers. The project manager from the mobile device division escalates a vendor-related risk to the program manager. After assessing the risk, the program manager determines that this risk may impact other projects within the program. However, this risk has a low degree of impact and probability of occurring. What should the program manager do first?
A Brainstorm with the project managers to develop an appropriate risk response.
B. Add the risk details and analysis to the program risk register.
C. Obtain a risk reserve from the executive sponsor, and execute a contingency plan.
D. Ignore this risk
 A biometrics firm has a facial recognition program with multiple components

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!