Question: A bottleneck is Multiple Choice a resource that has the smallest capacity. a resource that can affect the flow rate of a production process. a
A bottleneck is
Multiple Choice
a resource that has the smallest capacity.
a resource that can affect the flow rate of a production process.
a resource that can determine the capacity of the entire process.
All of these choices are correct.