Question: Process Analysis with One Flow Unit ( Bottleneck Analysis ) Consider a process consisting of three resources. Each product must go through processing on each

Process Analysis with One Flow Unit (Bottleneck Analysis)
Consider a process consisting of three resources. Each product must go through processing on each resource. Processing times and number of workers per resource are given below. Resources 1 and 3 have more than one worker working in parallel. For example, resource 1 has 2 workers, each of which can process one unit per 10 minutes.
Resource Processing Time [Min./Unit] Number of Workers
1102
261
3163
1. What is the bottleneck?
2. What is the process capacity?
3. What is the flow rate if demand is eight units per hour?
4. What is the utilization of each resource if demand is eight units per hour?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!