Question: a . Calculate Earned Value. b . Calculate the AC and PV . c . Calculate the CV , CPI, SV , SPI. d .

a. Calculate Earned Value.
b. Calculate the AC and PV.
c. Calculate the CV, CPI, SV, SPI.
d. Estimate how much money is needed to complete the remaining tasks.
e. Estimate (forecast) the total cost of the project ( EAC ?f) and variance at completion
(VACf).
f. How is this project doing (evaluate progress)?
Problem #5(20 points). Consider the following AON Network for a the given small project
with 6 activities.
a. Develop an AON/CPM Time-Constrained Network (no consideration of limited resources), with
its Start and End nodes, and calculate the ES; EF, LS, LF, total slack, and project duration.
Use the nodes used in this class only:
b. Assume that there are only TWO units of a limited resource. The quantity of units of the
limited resource required by each activity is given at the center of the "Legend" in the
AON network below. Your task is to develop a Resource-constrained schedule/loading
chart. You may delay the original EF of the project if necessary but keep all the required
precedence relationships. Use the parallel method to schedule activities, explain what rule is
used at each step, and make sure to include at the bottom of the resource-constrained
schedule two lines showing the number of units of the resource scheduled and the number of
units of the resource available.
c. Draw a new AON Network based on the previous and final resource constrained schedule (5
extra-points if no errors)
 a. Calculate Earned Value. b. Calculate the AC and PV. c.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!