Question: Project ABC Scope = 10 chairs @ $10.00 = $100.00 PV = Timeframe = 10 days AC = At the End of the 5 th
Project ABC
| Scope = 10 chairs @ $10.00 = $100.00 | PV = |
| Timeframe = 10 days | AC = |
| At the End of the 5th day 4 chairs were | EV = |
| Completed at a cost of $11.00 each | CV = |
|
| CPI= SV = |
|
| SPI= |
|
|
|
To install a 10,000 feet fence at a cost of $10.00/per foot. It is estimated that 500 feet of fence can be installed per week for a total of 20 weeks. After 12 weeks and with 50% of work completed $45,000.00 has been spent. Calculate the following and submit the exercise results in a Word document.
Budget at Completion (BAC) = ___________________________ #feet fence * cost/foot
Planned Value (PV) - ________________________________ BAC * (%time passed)
Earned Value (EV) _______________________________________ BAC * % completed
Actual Cost (AC) _________________________________________
Cost Variance (CV) _________________________________________ EV - AC
Schedule Variance (SV) _________________________________________ EV - PV
Cost Performance Index (CPI) ____________________________________ EV/AC %
Schedule Performance Index (SPI) ___________________________________ EV/PV %
Estimate at Completion (EAC) _____________________________________ BAC/CPI
Estimate to Complete (ETC) ____________________________________ EAC - AC
Variance at Completion (VAC) ____________________________________ BAC-EAC
To Complete Performance Index ______________________________ (BAC-EV)/(BAC/AC)