Question: a . Calculate the expected time and variance ( using the 9 5 percent confidence level ) for each activity. b . Using the expected

a. Calculate the expected time and variance (using the 95 percent confidence level) for each activity.
b. Using the expected times, determine the critical path and time for completion. Draw network diagram.
c. Calculate the probably that the project will finish in 60 days. Calculate the probably of completing the project in 65 days. Use 95% confidence level for both.
d. Management likes to fund projects that have an 85% chance (or probability) of attaining the plan. How many days are required for that chance?
\table[[Task,Pred.,\table[[Optimistic],[(days)]],Normal,Pessimistic],[2,-,6,10,15],[3,2,19,14,20],[4,2,5,12,16],[5,3,14,20,30],[6,3,4,12,25,35],[7,4,16,26,24],[8,5,4,10,25],[9,6,7,9,12,15]]
a . Calculate the expected time and variance (

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!