Question: A capacity constrained industrial process consists of 2 sequential steps. Step 2 has a total setup time of 40 minutes per batch while step 1

A capacity constrained industrial process consists of 2 sequential steps. Step 2 has a total setup time of

40 minutes per batch while step 1 has no setup time. The activity time for step 1 is 2 minutes per part, for step 2 is

1 minute per part? An entire batch must be processed at each step before the next step can begin to work on parts

from that same batch.

a.) Assuming a batch size of 20, what is the capacity (flow rate) of the entire process and what is the bottleneck?