Question: a manufacturing process consists of three sequential steps. step 1 has a capacity of 2 units / hour . step 2 has a capacity of
a manufacturing process consists of three sequential steps. step has a capacity of unitshour step has a capacity of unitshour step has a capacity of unithour at each step there is only one resource available. awhat is the capacity of this process In unitshourexplaion your answer. bassuming it is operating at full capacity, what is the utilization in step c assuming it is operating at full capacity, what is the cycle time in minutes. d suppose the takt time is minutes. is this process capacityconstrained, demandconstrained, neither, or both? explain your answer.