Question: A car wash is considering installing two lines. Each line can process 15 cars an hour, and they operate for 300 hours per month. With
A car wash is considering installing two lines. Each line can process 15 cars an hour, and they operate for 300 hours per month. With two lines, the design capacity is 15*2*300 = 9000 cars per month. Assuming they serve 18 cars an hour throughout the 300 hours of the month, what is the utilization