Question: a certain activity in a project was estimated to have an optimistic time of 4 weeks, a most likely time of 1 5 weeks, and

a certain activity in a project was estimated to have an optimistic time of 4 weeks, a most likely time of 15 weeks, and a pessimistic time of 23 weeks. the expected time of the activity is: