Question: A certain project has the following precedence relationships. Activity Immediate Predecessor(s) A - B - C A D C E A, B F D G
A certain project has the following precedence relationships.
| Activity | Immediate Predecessor(s) |
|---|---|
| A | - |
| B | - |
| C | A |
| D | C |
| E | A, B |
| F | D |
| G | D, E |
| H | F, G |
Draw the network diagram and submit its picture file.
What are the paths, from start to finish? List them all here:
The activity times are as follows:
| Activity | Activity Time (weeks) |
|---|---|
| A | 5 |
| B | 10 |
| C | 6 |
| D | 15 |
| E | 12 |
| F | 7 |
| G | 6 |
| H | 11 |
Use the above information to do your analysis in the next question.
How long is this project expected to last?