Question: A certain project has the following precedence relationships. Activity Immediate Predecessor(s) A - B - C A D C E A, B F D G

A certain project has the following precedence relationships.

Activity Immediate Predecessor(s)
A -
B -
C A
D C
E A, B
F D
G D, E
H F, G

Draw the network diagram and submit its picture file.

What are the paths, from start to finish? List them all here:

The activity times are as follows:

Activity Activity Time (weeks)
A 5
B 10
C 6
D 15
E 12
F 7
G 6
H 11

Use the above information to do your analysis in the next question.

How long is this project expected to last?