Question: A certain project has the following precedence relationships. Activity Immediate Predecessor(s) A - B - C A D C E A, B F D G
A certain project has the following precedence relationships.
| Activity | Immediate Predecessor(s) |
|---|---|
| A | - |
| B | - |
| C | A |
| D | C |
| E | A, B |
| F | D |
| G | D, E |
| H | F, G |
1)Draw the network diagram
2) What are the paths, from start to finish?
The activity times are as follows:
| Activity | Activity Time (weeks) |
|---|---|
| A | 7 |
| B | 9 |
| C | 6 |
| D | 13 |
| E | 12 |
| F | 3 |
| G | 5 |
| H | 10 |
3)How long is this project expected to last?
4)Calculate the earliest start/earliest finish, latest start/latest finish, and slack for each activity. Indicate them in a form of a network diagram
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
