Question: A certain project has the following precedence relationships. Activity Immediate Predecessor(s) A - B - C - D A, B E B F C, E
A certain project has the following precedence relationships.
| Activity | Immediate Predecessor(s) |
|---|---|
| A | - |
| B | - |
| C | - |
| D | A, B |
| E | B |
| F | C, E |
| G | D, E |
| H | F, G |
Draw the network diagram
What are the paths, from start to finish? List them all here: