Question: A certain project has the following precedence relationships. Activity Immediate Predecessor(s) A - B - C - D A, B E B F C, E

A certain project has the following precedence relationships.

Activity Immediate Predecessor(s)
A -
B -
C -
D A, B
E B
F C, E
G D, E
H F, G

Draw the network diagram

What are the paths, from start to finish? List them all here: