Question: A certain project is defined by the data given in the following table: Activity Predecessor Duration ( Weeks ) Workers A - 6 1 0

A certain project is defined by the data given in the following table:
Activity Predecessor Duration
(Weeks) Workers
A -610
B -38
C A 96
D B 54
E B 410
F D 28
G E 812
a) Create a plan for this project in MSP following our usual conventions and use MSPs
Project Summary Task feature to compute the overall project duration. Inspect the resulting
project network and make sure there are no dangling ends. [30] Assign the required workers
to each project activity, assuming that each activity starts as soon as possible. Save your
project plan under the file name HW9a.[20]
(50 points)
b) For the project plan you generated in part (a), rearrange the timing of select individual
activities within MSP to reduce the overall fluctuation in resource demand. Assume that
the project duration cannot be extended and remember that the precedence relationships
must not be violated. Save your revised project plan under the file name HW9b.
(25 points)
c) If there are only 20 workers available for this project, rearrange the timing of select
individual activities within MSP to ensure that the project can be completed as quickly as
possible but without violating the resource limit. In this case, the project duration may be
extended if necessary (but again making sure to maintain all precedence relationships).
Save your revised project plan under the file name HW9c.
(25 points)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!