Question: A Coach Sync occurs just before the draft plan review during PI Planning. The Scrum Master / Team Coach ( SM / TC ) from
A Coach Sync occurs just before the draft plan review during PI Planning. The Scrum MasterTeam Coach SMTC from one team raises an issue that Product Management just showed up to the planning area with a list of priority work. This work does not align with the Feature prioritization. What is the most likely planning antipattern causing this sudden impediment?
Prioritization by Product Management was performed autonomously not collaborativelyThere is strong alignment between business and marketingThere is no social network that Solution development relies onPlanning decisions have been centralized