Question: A company has 4 development projects that can be offered in bundles. The company has 3 potential suppliers that can handle all four projects. Table
A company has 4 development projects that can be offered in bundles. The company has 3 potential suppliers that can handle all four projects. Table 3 shows the bundles and the offered prices by the suppliers.
Table 3
|
| Price | |||||||||
| Suppliers/bundles | 1 | 2 | 3 | 4 | (2,3) | (1,4) | (1,2,4) | (1,3,4) | (2,3,4) | (1,2,3,4) |
| 1 | 5 | 8 | 9 | 8 | 15 | 11 | 19 | 16 | 19 | 27 |
| 2 | 6 | 9 | 10 | 9 | 16 | 12 | 18 | 17 | 19 | 26 |
| 3 | 7 | 7 | 12 | 10 | 17 | 12 | 18 | 20 | 20 | 26 |
By using Excel Solver find the best assignment that minimizes total cost