Question: A company has three components in a system and requires all three to be operational during the business hours of 8 a.m. to 5 p.m.,
A company has three components in a system and requires all three to be operational during the business hours of 8 a.m. to 5 p.m., Monday to Friday. The failure of component 2 occurs as follows:
Monday = 8 a.m. to 11 a.m.
Tuesday = No failure
Wednesday = 4 p.m. to 7 p.m.
Thursday = 5 p.m. to 8 p.m.
Friday = 1 p.m. to 2 p.m.
Calculate the availability of component 2.
Step by Step Solution
3.59 Rating (160 Votes )
There are 3 Steps involved in it
Availability system uptimesystem uptimesystem ... View full answer