Question: A comparative study was carried out on five planning software to verify the accuracy of the planned time for the development of projects, based on
A comparative study was carried out on five planning software to verify the accuracy of the planned time for the development of projects, based on various parameters such as the software flaw, the type of application, the complexity, the required coding, re-evaluation and validation. We have used a software that allows to plan the time required in the development of 10 programming projects whose various parameters are known
We postulate the simple regression rnodele between these two variables where y is the real time in days for the development of the programming projects and x, the planned time
the linear correlation coefficient is 0.695