Question: (a) Compute the required cycle time per unit in seconds. (b) Compute the minimum number of workstations required to produce 800 units per day. Group
(a) Compute the required cycle time per unit in seconds.
(b) Compute the minimum number of workstations required to produce 800 units per day. Group the tasks into workstations on the graph.
(c) What is the efficiency?
(d) If the time requirement for task E is 65 (instead of 55), what will be new number of workstations and efficiency?

A 20 4) A facility is trying to set up an assembly line, and has identified the various tasks, and their relationship to each other, as shown in the following table. Managers wish to produce 800 units per day, working two 8-hour shifts. (20 pts) Task Time to perform (sec.) B 30 25 D 10 E 55 F 30 G 25 H 40 20 A 55 E 30 B . 25 40 H G OG 30 10 D
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
