Question: A computer- based information system designed to manage production involving dependent demand inventories is: Computer aided manufacturing (CAM) Computer integrated manufacturing (CIM) Economic order quantity
- A computer- based information system designed to manage production involving dependent demand inventories is:
- Computer aided manufacturing (CAM)
- Computer integrated manufacturing (CIM)
- Economic order quantity (EOQ) model
- Material requirements planning (MRP)
- Economic run size (ERS)
- MRP systems translate the _______ into time-phased requirements for components.
- Master schedule
- Bill of materials
- Inventory records
- Assembly time chart
- Net- Requirements chart
- Which of the following is not a supporting goal or building block element for achieving a lean operation?
- Eliminate disruptions
- Make system flexible
- Eliminate waste
- Close vendor/supplier relationships
- Access to capital
- In project management, __________ an activity involves shortening the time it will take to complete the activity by increasing resources allocated to it.
- Hammering
- Expediting
- Crashing
- Hitting
- Speeding
- When using network diagrams for project management, the sequence of activities that has no slack time is called _________.
- Critical path
- Fast lane
- Priority trail
- Critical sequence
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock