Question: A computer - system installation project consists of eight activities. The immediate predecessors and activity times in weeks are shown below. Activity Immediate Predecessor (

A computer-system installation project consists of eight activities. The immediate predecessors and activity times in weeks are shown below.
Activity
Immediate Predecessor(s)
Activity Time
A
3
B
6
C
A
2
D
B, C
5
E
D
4
F
E
3
G
B, C
9
H
F, G
3
Enlarge Table
Draw the network for this project.
Identify the critical path(s).
What is the project completion time?
Construct an early-start date Gantt chart.
As a project manager, where would you focus your attention given your analysis?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!