A computer-system installation project consists of eight activities. The immediate predecessors and activity times in weeks are

Question:

A computer-system installation project consists of eight activities. The immediate predecessors and activity times in weeks are shown below.

A computer-system installation project consists of eight activities. The immediate

a. Draw the network for this project.
b. What are the critical-path activities?
c. What is the project completion time?