Question: a) Construct a network diagram using AON notation. b) Calculate the completion time for the project. c) Determine which activities are included on the critical
a) Construct a network diagram using AON notation.
b) Calculate the completion time for the project.
c) Determine which activities are included on the critical path.
Activity (A ) activity time (3) weeks [Immediate Predecessor (none)
Activity (B ) activity time (4) weeks [Immediate Predecessor (A)
Activity (C ) activity time( 2) weeks [Immediate Predecessor (B)
Activity (D ) activity time( 5) weeks [Immediate Predecessor (B)
Activity (E ) activity time( 4) weeks [Immediate Predecessor (C)
Activity (F ) activity time( 3) weeks [Immediate Predecessor (D)
Activity (G ) activity time( 2) weeks [Immediate Predecessor (E,F)