Question: Activity Activity Time (weeks) mmediate Predecessor(s) A 3 none B 4 A C 2 B D 5 B E 4 C F 3 D G

Activity

Activity Time (weeks)

mmediate Predecessor(s)

A

3

none

B

4

A

C

2

B

D

5

B

E

4

C

F

3

D

G

2

E,F

Construct a network diagram using AON notation.

  1. Then calculate the completion time for the project. Answer weeks
  2. Identify the critical path. A B D F C E G