Question: Activity Activity Time (weeks) mmediate Predecessor(s) A 3 none B 4 A C 2 B D 5 B E 4 C F 3 D G
| Activity | Activity Time (weeks) | mmediate Predecessor(s) |
| A | 3 | none |
| B | 4 | A |
| C | 2 | B |
| D | 5 | B |
| E | 4 | C |
| F | 3 | D |
| G | 2 | E,F |
|
|
|
|
Construct a network diagram using AON notation.
- Then calculate the completion time for the project. Answer weeks
- Identify the critical path. A B D F C E G