A. Construct a precedence diagram. B. Compute the

A. Construct a precedence diagram. B. Compute the four schedule dates (ESD, EFD, LSD, and LFD) and the floats (TF, FF,) for each activity. c. Identify the critical path D. Table of activities dates. DUR PREDECESSORS 0 A A No 5 10 15 20 25 30 35 40 45 50 55 60 65 70 ACT A B P L M Q N Y F J S V Q1 3 10 4 7 12 4 6 9 5 10 7 12 B PC P L,Q M Q N Y,FJ VS 4