Question: project management Problem No: 2 A. Construct a precedence diagram. B. Compute the four schedule dates (ESD, EFD, LSD, and LFD) and the floats (TF,

project management project management Problem No: 2 A. Construct a
Problem No: 2 A. Construct a precedence diagram. B. Compute the four schedule dates (ESD, EFD, LSD, and LFD) and the floats (TF, FF,) for each activity. C. Identify the critical path D. Table of activities dates. No PREDECESSORS 0 A 5 10 15 20 25 30 35 40 45 50 55 60 65 70 ACT B C P L M Q N Y F J S V Q1 DUR 3 10 4 7 12 4 6 9 5 10 7 12 15 4 A A B C P.C LQ M Q N Y,FJ VS